Legal Treatment Of Biomethane Injection Into Gas Grids .

1. Introduction

Biomethane injection into gas grids—often described as biomethane-to-grid (BtG) or, in India, increasingly as compressed biogas (CBG) injection into natural-gas pipelines and city-gas distribution (CGD) networks—involves upgrading biogas produced from organic waste until its methane concentration and other characteristics permit it to be transported through existing gas infrastructure.

Legally, the activity sits at the intersection of several regulatory fields:

renewable-energy regulation;

natural-gas pipeline regulation;

gas-quality and technical standards;

environmental and waste-management law;

health and industrial safety;

metering and balancing;

third-party network access;

contractual allocation of injection capacity and costs; and

sustainability and renewable-gas certification.

India has recently moved from a largely policy-based approach toward a more specific regulatory framework. On 11 February 2026, the Petroleum and Natural Gas Regulatory Board (PNGRB) approved guidelines specifically governing biogas/biomethane injection into Natural Gas Pipelines (NGPL) and City Gas Distribution networks. The guidelines expressly address design, construction, testing, commissioning, operation, maintenance, gas quality, metering, pressure regulation, monitoring, emergency isolation and safety.

The legal theory underlying grid injection is therefore not simply that biomethane is a renewable fuel. It is that, once appropriately upgraded and meeting prescribed specifications, biomethane can become a regulated gas commodity capable of being safely integrated into an existing natural-gas network.

 

2. Meaning and Nature of Biomethane Injection

Raw biogas normally contains methane together with carbon dioxide, water vapour, hydrogen sulphide and other contaminants. Before injection into a gas grid, it must generally undergo purification or upgrading.

The legal process can therefore be divided into:

Organic feedstock → anaerobic digestion → raw biogas → purification/upgrading → biomethane/CBG → compression and conditioning → metering → injection point → gas network → consumers

The central regulatory question is:

When does renewable biogas become legally acceptable gas for injection into a regulated natural-gas network?

The answer is normally determined by quality standards rather than by the origin of the molecule alone.

Consequently, the legal framework must regulate both:

the renewable character of the gas; and

its physical compatibility and safety within the gas network.

 

3. Indian Legal Framework

3.1 Petroleum and Natural Gas Regulatory Board Act, 2006

The principal institutional statute is the Petroleum and Natural Gas Regulatory Board Act, 2006.

The PNGRB regulates important aspects of the transportation and distribution of natural gas and provides the legal framework for authorization of natural-gas pipelines and CGD networks.

The Act is important for biomethane injection because injection into an existing NGPL or CGD network cannot be treated merely as a private commercial transaction. The injection facility becomes functionally connected to regulated gas infrastructure.

PNGRB's existing regulatory framework includes regulations dealing with:

natural-gas pipeline authorization;

CGD network authorization;

access codes;

technical and safety standards;

pipeline tariffs;

common-carrier and contract-carrier arrangements; and

integrity-management systems.

PNGRB continues to maintain separate regulatory frameworks for natural-gas pipelines and CGD networks.

 

4. The 2026 PNGRB Biomethane/CBG Injection Guidelines

A major development occurred in February 2026.

PNGRB approved the Guidelines for Biogas (Biomethane) Injection in Natural Gas Pipelines/City Gas Distribution Network & its Facilities.

The guidelines apply to facilities associated with injection of biomethane into NGPL or CGD infrastructure up to the injection point. They specifically address:

material selection;

planning and design;

installation;

inspection;

testing;

commissioning;

operation;

maintenance; and

safety of injection facilities.

This represents an important shift from treating CBG merely as a fuel product toward treating its physical integration with gas infrastructure as a regulated activity.

 

5. Gas Quality as the Principal Legal Gateway

One of the most important principles is that renewable origin does not automatically establish grid compatibility.

The 2026 PNGRB guidelines require biomethane injected into NGPL/CGD networks to comply with relevant requirements under:

PNGRB Access Code for Common Carrier/Contract Carrier Natural Gas Pipelines;

PNGRB Access Code for City or Local Natural Gas Distribution Networks;

IS 16087:2025 — Biogas (Biomethane) Specification; and

other applicable technical standards.

Where different specifications apply, the more stringent requirement is to be followed.

This creates a legal principle of quality equivalence:

Renewable gas may enter a conventional gas network only when its composition and physical characteristics are sufficiently compatible with the network's safety and operational requirements.

 

6. Dew Point, Temperature and Contaminants

The 2026 guidelines establish important operational requirements.

Injected biomethane must satisfy specified limits relating to:

hydrocarbon dew point;

water dew point;

gas temperature;

methane content;

carbon dioxide;

oxygen;

hydrogen sulphide; and

other relevant contaminants.

The guidelines specify a maximum hydrocarbon dew point and water dew point of 0°C at pipeline operating pressure and a maximum gas temperature of 55°C.

This is legally significant because poor gas quality can create:

corrosion;

condensation;

pipeline damage;

appliance malfunction;

heating-value variation;

toxic exposure;

pressure-management problems; and

network integrity risks.

Thus, the producer bears a continuing quality-assurance obligation, not merely a one-time certification obligation.

 

7. Continuous Monitoring and Automatic Isolation

The PNGRB framework requires an online gas-quality monitoring system.

The 2026 guidelines require the producer to install appropriate analysers and monitoring equipment. Gas analysers/gas chromatographs must record relevant parameters, and historical data must be retained. The guidelines also require communication arrangements enabling the CGD or NGPL operator to monitor relevant parameters remotely.

This produces an important regulatory concept:

Continuous compliance

The producer must demonstrate not merely:

"The gas was compliant when the plant was commissioned."

Instead, the regulatory expectation is:

"The gas remains compliant throughout injection."

Automatic isolation mechanisms are therefore required where gas quality deviates from prescribed limits.

The guidelines contemplate automatic isolation for events including:

deviation in gas quality;

excessive dew point;

pressure deviation;

inadequate odorization where required;

loss of power to critical analytical equipment; and

methane detection exceeding specified safety thresholds.

 

8. Pressure Regulation

Biomethane cannot simply be introduced into a pipeline because it satisfies chemical specifications.

It must also be introduced at an appropriate pressure.

The PNGRB framework requires pressure-regulating equipment, including appropriate protection against:

over-pressure;

under-pressure;

reverse flow; and

unsafe pressure fluctuations.

The injecting pressure is to be agreed between the producer and NGPL/CGD entity but must remain within the maximum allowable operating pressure of the receiving pipeline.

The legal significance is that network integrity takes precedence over unilateral injection rights.

A producer cannot claim an absolute right to inject merely because its biomethane satisfies the applicable gas-quality standard.

 

9. Metering and Measurement

Biomethane injection also creates an important legal problem:

How much gas was actually injected?

This affects:

payment;

balancing;

network charges;

renewable-gas accounting;

contractual compliance;

taxation;

certificates; and

dispute resolution.

The 2026 guidelines therefore require metering arrangements capable of monitoring real-time gas flow and related parameters. Metering systems are expected to comply with applicable standards and to be calibrated through appropriate accredited laboratories.

This makes metering evidence legally important in disputes concerning:

under-delivery;

over-injection;

gas-quality claims;

payment;

imbalance;

network losses; and

contractual penalties.

 

10. Odorization

Odorization has a direct public-safety function.

Natural gas is naturally difficult to detect by smell. Odorants therefore assist consumers and emergency personnel in identifying leakage.

The PNGRB guidelines require appropriate odorization arrangements where applicable and contemplate use of odorants such as ethyl mercaptan or tetrahydrothiophene, preferably consistent with the odorant used by the receiving CGD entity.

However, the requirements differ according to the type of receiving infrastructure. For example, the guidelines state that odorization is not required for injection into a steel NGPL network, while MDPE applications require appropriate odorization.

 

11. Liability for Off-Specification Gas

One of the most important contractual and regulatory issues is allocation of responsibility when injected gas is outside specification.

A typical legal arrangement should identify:

who tests the gas;

which test controls in case of conflict;

sampling methodology;

testing frequency;

acceptable tolerance;

automatic shut-off procedures;

rejection rights;

emergency procedures;

compensation for damage;

responsibility for contamination;

network cleaning or remediation costs; and

dispute-resolution procedures.

The 2026 PNGRB guidelines expressly contemplate independent sampling and testing by the CGD/NGPL entity, including testing through NABL-accredited laboratories at defined intervals and in response to quality complaints.

This is an example of regulatory co-monitoring: both the producer and network operator have responsibilities.

 

12. Network Access and Non-Discrimination

A central legal question is whether a biomethane producer has a right to access an existing gas grid.

This requires distinguishing between:

a right to request connection;

a right to technically feasible connection;

a right to capacity;

a right to transport gas after connection; and

a right to receive a particular tariff.

These are not necessarily identical.

Indian natural-gas jurisprudence establishes that PNGRB's statutory authority depends upon the particular category of pipeline or network and the powers actually granted by Parliament.

 

13. PNGRB v. Indraprastha Gas Ltd.

A leading Supreme Court decision is:

Petroleum & Natural Gas Regulatory Board v. Indraprastha Gas Ltd., (2015) 9 SCC 209.

The Supreme Court examined the statutory limits of PNGRB's authority over city gas distribution networks.

The Court held that PNGRB did not possess the statutory power to impose the particular network tariff and CNG compression-charge regime at issue in the case merely through regulations where the statutory framework did not confer that power. The decision illustrates a broader administrative-law principle:

A regulator cannot create substantive regulatory powers through subordinate legislation when those powers have not been granted by the parent statute.

 

Relevance to biomethane

The case is not a biomethane-injection case. Nevertheless, it is highly relevant when determining whether PNGRB may:

impose an injection tariff;

require particular access arrangements;

allocate connection costs;

prescribe transportation charges; or

regulate commercial terms.

The legal source of the regulatory power must therefore be identified carefully.

 

14. GAIL (India) Ltd. v. PNGRB

Another important decision is:

GAIL (India) Ltd. v. Petroleum & Natural Gas Regulatory Board, Supreme Court, 13 January 2016.

The case concerned access to common-carrier capacity and alleged discriminatory treatment.

The Supreme Court emphasized the importance of examining the applicable regulatory provisions before determining whether conduct relating to common-carrier capacity constitutes prohibited discrimination or a restrictive trade practice.

Application to biomethane

The case provides a useful legal foundation for examining whether a gas-network operator can legitimately refuse or restrict biomethane access.

Relevant considerations include:

available capacity;

technical feasibility;

applicable access regulations;

objective quality requirements;

non-discrimination;

contractual arrangements; and

statutory authority.

A network operator should therefore avoid arbitrary refusal of biomethane access while retaining legitimate rights to protect network safety and integrity.

 

15. GAIL and the Concept of Common-Carrier Access

The broader Indian legal framework distinguishes between:

Common carrier

Infrastructure made available to multiple users under regulated access arrangements.

Contract carrier

Infrastructure operated under contractual transportation arrangements.

CGD network

An interconnected network serving consumers within an authorized geographical area.

This distinction matters because a biomethane producer seeking to inject gas into a network is not necessarily asking merely to sell gas. It may also be seeking regulated access to infrastructure.

The legal rights of the producer therefore depend on the classification and authorization of the receiving infrastructure.

 

16. Great Eastern Energy Corporation and Pipeline Authorization

Indian litigation involving Coal Bed Methane (CBM) provides another useful analogy.

In Great Eastern Energy Corporation Ltd. v. Union of India & Anr., the Delhi High Court considered PNGRB's action concerning a pipeline used for transportation of CBM and the requirement of authorization under the PNGRB Act.

Although CBM is not biomethane, both cases demonstrate an important regulatory proposition:

The legal character of the gas and the legal character of the pipeline are separate questions.

A renewable or privately produced gas does not automatically make its transportation infrastructure exempt from the statutory pipeline regime.

 

17. Environmental Regulation

Biomethane projects are also subject to environmental regulation.

The project may involve:

organic waste;

sewage;

agricultural residues;

municipal solid waste;

animal waste;

digestate;

wastewater;

air emissions;

odour;

groundwater impacts; and

waste-treatment activities.

Accordingly, compliance with gas-grid rules does not eliminate obligations under environmental law.

The 2026 PNGRB guidelines expressly contemplate obtaining applicable statutory clearances, including permissions involving the District Magistrate, PESO and State Pollution Control Board where applicable.

 

18. Safety Law and PESO Regulation

Because biomethane is combustible and is often compressed, safety regulation becomes central.

Depending on the configuration, legal requirements may concern:

pressure vessels;

gas cylinders;

compressors;

hazardous areas;

storage cascades;

transportation;

electrical installations;

fire protection;

emergency shutdown;

hazardous-goods transport.

The PNGRB guidelines require compliance with applicable PESO and Gas Cylinder Rules requirements for relevant compressed-gas facilities and transportation arrangements.

Thus, the legal treatment of biomethane injection is inherently multi-regulatory.

 

19. European Union Comparative Law

The EU has developed a particularly important legal approach to renewable-gas grid access.

Directive (EU) 2024/1788 contains explicit provisions concerning renewable gas and biomethane.

It requires distribution system operators to ensure the long-term ability of their systems to meet reasonable demands for natural-gas distribution, including biomethane injection. It also establishes non-discrimination principles and requires transparent procedures for connection of renewable-gas production facilities.

Importantly, economically reasonable and technically feasible connection requests for renewable and low-carbon gas production facilities cannot simply be rejected except under the conditions specified by the Directive.

The EU model therefore moves toward a principle of:

regulated access + technical feasibility + non-discrimination + gas-quality management.

 

20. EU Rules on Connection Procedures

The EU framework also emphasizes procedural transparency.

Distribution-system operators are expected to have:

transparent connection procedures;

efficient connection processes;

regulatory oversight;

appropriate tariffs;

reasonable timelines; and

non-discriminatory treatment.

For biomethane specifically, Member States are directed to encourage reasonable time limits for assessment of injection requests, offers and implementation of connections.

This demonstrates a broader legal trend:

Renewable-gas producers increasingly receive a legally protected pathway to network connection, but that pathway remains conditioned by network security and technical feasibility.

 

21. E.ON Biofor Sverige AB v. Statens Energimyndighet

A particularly important European case is:

E.ON Biofor Sverige AB v. Statens Energimyndighet, Case C-549/15, Court of Justice of the European Union, 22 June 2017.

The case concerned sustainable biogas transported through interconnected gas networks and the operation of the EU sustainability-certification/mass-balance framework.

The CJEU held that EU law did not itself impose a general obligation on Member States to authorize imports of sustainable biogas through interconnected national gas networks. However, it also held that national administrative treatment excluding a mass-balance arrangement for sustainable biogas transported through interconnected networks could conflict with the EU free-movement rules where comparable national-network treatment was permitted.

Legal significance

The case establishes an important principle for renewable gas:

Physical transportation of gas through an interconnected network and legal attribution of renewable characteristics are related but distinct questions.

A molecule physically enters a common gas network, but legal systems still need rules for determining:

origin;

sustainability;

ownership;

renewable attributes;

mass balance;

certification; and

cross-border accounting.

 

22. UK Comparative Law

The UK provides another useful model.

The Gas Safety (Management) Regulations 1996, as amended, regulate the safe management and composition of gas conveyed through relevant networks.

The 2023 amendments broadened the range of gas specifications that can be conveyed and addressed biomethane-related pipeline arrangements. HSE explains that the amendments were intended to permit a wider range of gas specification to enter the gas network.

The UK's approach demonstrates an important regulatory technique:

Rather than creating a completely separate biomethane network, existing gas-safety rules are adapted to accommodate renewable gas.

 

23. Network Entry Agreements

The UK framework also illustrates the importance of contractual network-entry arrangements.

Government guidance on biomethane injection states that biomethane for injection into the gas grid must:

be of acceptable quality;

satisfy the Gas Safety (Management) Regulations;

comply with applicable product standards; and

be supplied under a Network Entry Agreement established by a gas transporter under the applicable gas-network code.

This is conceptually important for India.

A future Indian biomethane-to-grid market will likely require increasingly sophisticated agreements dealing with:

gas specifications;

pressure;

metering;

injection capacity;

imbalance;

curtailment;

testing;

ownership;

payment;

environmental attributes;

liability; and

termination.

 

24. Grid Injection as a Form of Functional Interoperability

Biomethane injection can be understood legally as an issue of infrastructure interoperability.

The producer owns one system:

biogas plant + upgrading plant + compressor + metering

The network operator controls another:

pipeline + pressure system + consumers + balancing system

The injection point is therefore a legal boundary between two infrastructures.

The law must establish:

technical standards;

ownership boundaries;

operational responsibility;

risk allocation;

metering responsibility;

quality responsibility;

emergency responsibility; and

financial responsibility.

The PNGRB 2026 guidelines expressly address this interface through requirements concerning pressure regulation, metering, monitoring, isolation, safety and coordination between CBG producers and network entities.

 

25. Curtailment of Biomethane Injection

A difficult legal question arises where:

the biomethane plant can produce gas;

the gas satisfies quality standards; but

the network cannot physically absorb additional gas.

This can occur when local demand is low or when reverse-flow capacity is unavailable.

EU regulatory analysis has identified this problem because distribution networks can experience minimum-demand constraints while biomethane production remains relatively stable. Reverse-flow infrastructure may therefore be required to move renewable gas toward transmission networks.

The legal contract should therefore distinguish between:

Technical curtailment

Necessary for safety or network integrity.

Economic curtailment

Caused by capacity or commercial constraints.

Regulatory curtailment

Required by an order or regulatory rule.

The consequences for compensation should be expressly established.

 

26. Ownership of Injected Biomethane

Another important legal issue is ownership.

A biomethane injection agreement should establish the precise point at which title passes.

Possible structures include:

Producer → injection point → network operator

or:

Producer retains title while gas is transported as a network commodity.

This matters because the same gas molecules become physically mixed with other gases.

Consequently, contractual law increasingly needs to recognize that physical identity and legal ownership can diverge.

This is one reason mass-balance systems and certificate systems are important in renewable-gas markets.

 

27. Renewable Attributes and Biomethane Certificates

Biomethane possesses two potentially distinct legal values:

Commodity value

The physical gas itself.

Environmental attribute

The renewable or emissions-reduction characteristic associated with its production.

A legal framework must determine whether these two attributes:

remain together;

may be separated;

may be transferred independently;

may be counted by another entity; or

may be used for renewable-energy compliance.

The E.ON Biofor decision demonstrates how mass-balance and sustainability accounting can become legally significant when renewable gas is transported through interconnected gas networks.

 

28. Consumer Protection

Grid-injected biomethane may ultimately be supplied to:

households;

commercial establishments;

industries;

CNG stations; and

other gas consumers.

Consumers therefore have an interest in:

consistent heating value;

safe gas composition;

adequate odorization;

reliable supply;

accurate billing; and

protection from unsafe contamination.

Gas-quality regulation is consequently not merely an industrial matter. It is also a form of consumer protection law.

 

29. Regulatory Liability

Potential liability can arise at several levels.

Producer liability

For:

off-specification gas;

inadequate purification;

failure of monitoring systems;

contamination;

defective equipment;

inaccurate metering.

Network-operator liability

For:

negligent network operation;

improper acceptance of gas;

inadequate network monitoring;

failure to isolate dangerous gas.

Contractor liability

For:

defective construction;

installation failures;

maintenance failures.

Environmental liability

For:

waste-treatment failures;

pollution;

improper disposal of digestate.

The contract should not attempt to eliminate statutory liability through private clauses where the law imposes mandatory obligations.

 

30. Legal Character of PNGRB's 2026 Guidelines

The 2026 guidelines are particularly significant because they provide detailed technical and safety requirements specifically for biomethane injection.

They require, among other things:

online gas analysis;

automatic isolation;

pressure regulation;

metering;

gas-leak detection;

odorization where applicable;

HAZOP and QRA studies;

emergency-response planning;

statutory approvals;

management-of-change procedures; and

coordination between CBG producers and NGPL/CGD operators.

Nevertheless, one must distinguish between:

statutory provisions;

binding PNGRB regulations;

technical standards;

guidelines; and

contractual requirements imposed by the network operator.

Their legal force is not necessarily identical.

This distinction is especially important when challenging a requirement before a court or tribunal.

 

31. Key Legal Principles

The legal treatment of biomethane injection can therefore be summarized through the following principles.

Principle 1 — Renewable status is not sufficient

Biomethane must satisfy technical and safety requirements before entering the grid.

Principle 2 — Gas quality is a continuing obligation

Compliance must be continuously monitored rather than established only at commissioning.

Principle 3 — Network integrity is paramount

Injection may be restricted where necessary to protect pipeline safety and system integrity.

Principle 4 — Access must operate within statutory authority

Network-access rights and tariffs must derive from the applicable statutory and regulatory framework.

Principle 5 — Non-discrimination matters

A network operator should apply objective technical and commercial criteria rather than discriminatory criteria.

Principle 6 — Measurement must be legally reliable

Metering and laboratory testing are central to allocation of commercial and regulatory responsibility.

Principle 7 — Renewable attributes require separate accounting

Physical gas flow and renewable certification can constitute separate legal concepts.

Principle 8 — Environmental compliance remains necessary

Gas-grid approval does not replace environmental or waste-management approvals.

Principle 9 — Contracts are essential

Network Entry Agreements or equivalent arrangements should allocate risks at the injection interface.

Principle 10 — Regulatory powers remain constrained by statute

The Supreme Court's PNGRB jurisprudence demonstrates that the regulator cannot assume powers beyond the enabling legislation.

 

32. Important Case Laws

CaseLegal principleRelevance to biomethane
PNGRB v. Indraprastha Gas Ltd., (2015) 9 SCC 209Regulatory powers must remain within the PNGRB Act; statutory tariff powers cannot be expanded merely by regulationLimits the legal basis for imposing tariffs or obligations on gas-network participants
GAIL (India) Ltd. v. PNGRB, Supreme Court, 2016Common-carrier access and alleged discriminatory treatment must be examined under the applicable regulatory frameworkRelevant to third-party biomethane access
Great Eastern Energy Corp. v. Union of India, Delhi HC, 2015Gas transportation infrastructure can attract PNGRB authorization requirementsUseful analogy concerning private gas pipelines
E.ON Biofor Sverige AB v. Statens Energimyndighet, C-549/15 (CJEU, 2017)Renewable-gas mass balance and cross-border network transportation must comply with EU free-movement principlesImportant for renewable-gas certification and network accounting
GAIL/PNGRB litigation concerning common-carrier capacityRegulatory access, capacity and non-discrimination depend upon the statutory/regulatory classification of the pipelineRelevant to grid-access disputes

The first three cases are particularly useful for an Indian legal analysis, while E.ON Biofor is highly valuable for comparative renewable-gas law.

 

33. Emerging Legal Issues

The expansion of biomethane injection will generate several new legal questions.

A. Mandatory grid connection

Should a technically compliant biomethane plant receive a statutory right to connection?

B. Cost allocation

Who pays for:

pipeline extension;

compressor;

metering;

upgrading;

reverse-flow equipment;

testing equipment?

C. Capacity allocation

How should scarce injection capacity be allocated between competing producers?

D. Curtailment compensation

Should producers receive compensation when technically compliant gas is rejected for network constraints?

E. Renewable attribute ownership

Who owns the environmental benefit after the physical gas enters the grid?

F. Gas-quality disputes

Which laboratory's measurement should be legally conclusive?

G. Cross-border biomethane

How should renewable gas transported through interconnected gas networks be certified?

H. Liability for network contamination

Who bears the loss if off-specification gas damages appliances or infrastructure?

I. Digital monitoring

What legal status should be given to automated gas-quality data, sensors and remote shut-off systems?

J. Climate accounting

How should lifecycle emissions from feedstock collection, upgrading, compression and transportation be calculated?

 

34. Conclusion

The legal treatment of biomethane injection into gas grids is evolving from a simple renewable-energy support question into a sophisticated field of energy-infrastructure regulation.

In India, the 2026 PNGRB guidelines represent a significant development by expressly regulating biomethane/CBG injection into NGPL and CGD networks. They establish requirements concerning gas quality, pressure, metering, monitoring, odorization, automatic isolation, hazardous-area safety, emergency procedures and statutory approvals.

The central legal principle is that biomethane should be treated as a renewable gas capable of using existing gas infrastructure, but only through a controlled regulatory interface.

The Indian case law on natural-gas pipelines supplies the broader legal architecture. PNGRB v. Indraprastha Gas Ltd. demonstrates that regulatory agencies must operate within the authority granted by Parliament, while GAIL v. PNGRB illustrates the importance of regulated and non-discriminatory access to common-carrier capacity.

Comparatively, the EU has moved further toward explicit renewable-gas connection rights and non-discriminatory access, while the UK has incorporated biomethane into its gas-safety and network-entry framework.

Accordingly, the future legal architecture for biomethane injection should combine:

renewable-energy recognition + mandatory quality standards + network-access rules + safety regulation + transparent metering + contractual risk allocation + renewable-attribute accounting + environmental safeguards.

The ultimate objective is not simply to permit biomethane to enter a pipeline. It is to create a legally reliable system in which renewable gas can be safely integrated, fairly traded, accurately measured and properly attributed within an interconnected gas network.

Clarify the Indian statutory hierarchyAdd a dedicated regulatory-process section

LEAVE A COMMENT