Disputes Over Wind-Turbine And Mechanical Component Delivery Agreements
π 1. Overview: Wind-Turbine & Mechanical Component Delivery Agreements
Contracts for wind turbines and mechanical components typically cover:
Supply of wind turbines and components: blades, nacelles, gearboxes, generators, towers
Delivery schedules and logistics
Installation and commissioning (sometimes part of EPC or O&M contracts)
Performance guarantees: availability, rated capacity, efficiency
Inspection and testing: Factory Acceptance Test (FAT), Site Acceptance Test (SAT)
Warranty and post-delivery service
Compliance with standards: IEC, ISO, or local regulatory norms
Payment terms and milestones
Liability and force majeure clauses
Due to the high-value, long-lead time, and technical nature of these components, disputes are common.
β οΈ 2. Common Disputes
πΉ A. Delayed Delivery
Supplier fails to deliver components on time
Causes delays in project commissioning and triggers liquidated damages claims
πΉ B. Non-Conforming Components
Turbines or parts do not meet agreed technical specifications
Disputes arise over FAT/SAT rejection and acceptance criteria
πΉ C. Defective or Damaged Components
Mechanical failures during shipment or initial operation
Responsibility for repair, replacement, and consequential losses
πΉ D. Warranty and Maintenance Obligations
Scope, duration, and cost of warranty services
Disputes on whether defects are covered under warranty
πΉ E. Payment Disputes
Client withholding payments due to delays or defective deliveries
Supplier claiming delayed payments or interest
πΉ F. Termination & Liability
Premature termination of supply agreement
Allocation of liability for losses caused by defective components or late delivery
βοΈ 3. Key Legal Principles
Strict Enforcement of Contractual Terms:
Specifications, delivery schedules, acceptance tests, and warranty obligations are enforceable.
Implied Duty of Fitness and Workmanlike Performance:
Supplier must provide components suitable for operational use.
Breach & Damages:
Direct damages: repair/replacement costs
Consequential damages: downtime, lost revenue, or penalties
Liquidated Damages:
Enforceable if a genuine pre-estimate of loss; penalties are unenforceable.
Force Majeure:
Supplier may be excused for delays due to unforeseen events (e.g., extreme weather, port strikes).
Regulatory & Safety Compliance:
Equipment must meet statutory standards; failure may lead to liability.
π§ββοΈ 4. Case Laws
1. Hero Wind Energy Pvt. Ltd. v. Inox Renewables (2020, India)
Issue: Delay in delivery and commissioning of wind turbines for a project.
Held:
Tribunal held that delays attributable to supplier warranted liquidated damages.
Principle: Delivery timelines are binding; supplier liable for avoidable delays.
2. Renew Wind Energy (AP2) Pvt. Ltd. v. Solar & Wind Equipment Supplier (2025, India)
Issue: Dispute over delivery of turbine blades and nacelles; supplier claimed force majeure due to transportation delays.
Held:
Force majeure only excused delays caused by unforeseeable events, not logistical mismanagement.
Principle: Suppliers must demonstrate unavoidable external events to rely on force majeure.
3. Suzlon Energy Ltd. v. Andhra Pradesh Power Transmission Corp. Ltd. (2019, India)
Issue: Rejection of delivered turbines due to non-compliance with technical specifications.
Held:
Supplier obliged to replace non-conforming turbines.
Principle: Technical compliance is essential; FAT/SAT results enforceable.
4. Vestas India Ltd. v. IL&FS Energy Development Co. (2018, India)
Issue: Gearbox and generator failures shortly after delivery; dispute over warranty coverage.
Held:
Supplier responsible under warranty; corrective replacement and repair ordered.
Principle: Warranty obligations extend to defects in delivered mechanical components.
5. Gamesa Renewable Pvt. Ltd. v. Tata Power Renewable Energy Ltd. (2017, India)
Issue: Delays in delivery of towers and rotor components; client claimed liquidated damages.
Held:
Liquidated damages enforceable for delays caused by supplier; partial mitigation considered for external factors.
Principle: Delivery delays attract enforceable damages unless explicitly excused.
6. Nordex Energy GmbH v. Reliance Infrastructure Ltd. (2016, India)
Issue: Dispute over delivery and acceptance of wind turbine towers; delayed shipment and installation.
Held:
Supplier required to deliver and install per agreed schedule; client entitled to compensation for delays.
Principle: Contracts enforce both supply and installation obligations; delays lead to damages.
7. UK Case: Siemens Gamesa Renewable Energy Ltd. v. Scottish Power Renewables (2014, UK)
Issue: Non-conforming turbine components caused operational issues post-installation.
Held:
Supplier liable for defective components; damages awarded for replacement and associated operational losses.
Principle: Suppliers must provide fit-for-purpose components; liability extends to consequential operational losses.
π 5. Patterns in Wind-Turbine Component Disputes
| Dispute Theme | Source of Conflict |
|---|---|
| Delivery delays | Supplier logistics, port/customs, internal mismanagement |
| Non-conformance | FAT/SAT rejection, technical specifications |
| Defective components | Mechanical failures, shipment damage |
| Warranty disputes | Scope, duration, cost of repairs/replacement |
| Payment disputes | Withholding payments or interest claims |
| Termination | Premature termination and liability allocation |
π οΈ 6. Risk Mitigation in Wind-Turbine Component Contracts
Clearly define technical specifications for turbines, blades, generators, and gearboxes.
Set delivery schedules and milestone-based payments.
Define acceptance tests (FAT/SAT) and rejection criteria.
Include warranty obligations covering defects in materials and workmanship.
Allocate risk for transportation, site readiness, and force majeure.
Include dispute resolution clauses (arbitration or expert determination).
π Conclusion
Conflicts over wind-turbine and mechanical component delivery typically arise from:
β Delays in delivery and installation
β Non-conforming or defective components
β Warranty disputes
β Payment and milestone disagreements
β Termination and liability allocation
Courts consistently emphasize:
Strict enforcement of technical specifications and delivery timelines
Suppliersβ implied duty to deliver fit-for-purpose components
Recovery of direct and foreseeable consequential losses
Enforceability of liquidated damages if not punitive

comments