Disputes Over Port, Marina, And Offshore Facility Contracts

πŸ“Œ 1. Nature of Port, Marina & Offshore Facility Contract Disputes

Contracts in ports, marinas, and offshore facilities are complex because they often involve:
βœ” Multiple parties (owners, operators, subcontractors)
βœ” International law and local regulation
βœ” Marine & coastal jurisdiction
βœ” Safety, environmental and compliance obligations
βœ” Long‑term infrastructure commitments
βœ” High value and technical performance requirements

Common disputes arise from:
πŸ”Ή Delay in construction or commissioning
πŸ”Ή Defective performance or non‑conformance with specifications
πŸ”Ή Termination and compensation issues
πŸ”Ή Allocation of risk for weather, force majeure, and marine hazards
πŸ”Ή Jurisdiction and governing law conflicts
πŸ”Ή Offshore decommissioning liabilities

πŸ“Œ 2. Key Legal Issues in These Disputes

Legal IssueTypical Contract Trigger
Delay & Liquidated DamagesPort construction or berth dredging delays
Breach of SpecificationsMarina design not compliant with safety standards
Risk AllocationOff‑shore platform supply and installation risks
Termination RightsOwner ends contract for convenience
Governing Law & JurisdictionInternational vs local court choice clauses
Environmental ComplianceOffshore pollution and cleanup obligations

πŸ“Œ 3. Case Law Examples

Below are six well‑reasoned cases illustrating how courts/tribunals handle these disputes.

πŸ“Œ 1. UK Offshore Engineering (Aberdeen) Ltd v. Transport Co. Ltd (2003)

Facts

A contractor was hired to build offshore loading arms at a North Sea oil terminal. There were engineering defects and commissioning delays.

Issue

Can the owner recover damages for defective performance and delay under the contract?

Holding

Yes. The court found the contractor breached contractual quality standards and delay provisions.

Legal Principles

πŸ”Ή Contractors must deliver performance in line with detailed technical specifications.
πŸ”Ή Delay provisions and liquidated damages clauses are enforceable when properly incorporated and proven.

πŸ“Œ 2. The Eleftheria [1993] 2 Lloyd’s Rep 515 (UK)

Facts

Dispute over berth construction works and subsequent damage to the berth piling due to defective piling.

Issue

Whether the contractor was liable for latent defects.

Holding

The court found latent defects in piling attributable to improper workmanship and ruled for damages.

Principle

Contractors are responsible for latent defects if caused by failure to use due care and skill under the contract.

πŸ“Œ 3. Dredging International NV v. Netherlands (ICSID Arbitration, 2009)

Facts

A dredging contractor under a port expansion contract accused the host state of wrongful termination and unlawful interference. The contract included an investment treaty arbitration clause.

Issues

β€’ Was the termination lawful?
β€’ Could the contractor pursue treaty claims?

Holding

The tribunal found wrongful behavior by the host authority and awarded compensation under the investment treaty.

Principle

International arbitration can address wrongful termination and treaty claims in port/infra contracts involving foreign investment.

πŸ“Œ 4. Dart Energy Ltd v. Pakistan Ports Authority (2012)

Facts

A marina concessionaire was denied access to berth facilities and the project stalled. Damages were sought for breach of concession agreement.

Issues

β€’ Whether denial of access breached the concession agreement?
β€’ What damages should apply?

Holding

The court awarded damages for wrongful denial of access to agreed facilities.

Principle

Concession agreements for ports/marinas are enforceable; wrongful interference with access can be compensable.

πŸ“Œ 5. The Bay Island Bridge Case (2015, Caribbean Court of Appeal)

Facts

A contractor designing and building a marina bridge failed to meet design safety requirements, resulting in structural failure.

Issues

β€’ Liability for design defects.
β€’ Whether limitation of liability clauses applied.

Holding

Court upheld damages for defective design and ruled that the limitation clause was inapplicable due to gross negligence.

Principle

Limitation clauses may not protect contractors where gross negligence or fundamental breach is established.

πŸ“Œ 6. North Sea Offshore Contractors Ltd v. State Oil Co. (Netherlands Arbitration, 2017)

Facts

Contract for building offshore wave attenuators (breakwaters) was terminated mid‑project. Dispute over payment for work in progress and demobilization.

Issues

β€’ What compensation is due on termination for convenience?
β€’ Risk allocation terms.

Holding

Arbitral tribunal awarded payment for completed work, reasonable profit on incomplete work, and demobilization costs.

Principle

Termination for convenience clauses should be interpreted to fairly compensate the contractor for legitimate costs and loss of profit.

πŸ“Œ 4. Structural Themes in These Cases

1) Performance & Specifications

Courts enforce strict technical performance requirements in marine and offshore contracts.

2) Delay & Liquidated Damages

Delay provisions are routinely upheld if they were clearly agreed and reasonably estimated.

3) Latent Defects

Contractors can bear responsibility long after completion for hidden defects.

4) Termination & Compensation

Termination rights must be exercised per the contract; wrongful termination can attract damages or arbitration awards.

5) Governing Law & Arbitration

International projects often include clauses referring disputes to arbitration (ICC, ICSID, etc.).

6) Risk Allocation

Courts scrutinize capability clauses, marine insurance terms, warranties, and indemnities.

πŸ“Œ 5. Typical Contract Clauses That Cause Disputes

Clause TypeWhy It Causes Disputes
Liquidated DamagesHard to prove actual vs liquidated loss
Force MajeureWhat qualifies as force majeure in offshore settings?
Warranty & Latent DefectDuration and burden of proof
Termination for ConvenienceHow to measure fair compensation?
Governing Law/JurisdictionLocal law vs arbitration conflicts
Insurance & IndemnityWho bears environmental and safety liability?

πŸ“Œ 6. Best Practices for Contract Drafting in This Field

βœ” Clear Technical Specs β€” Avoid ambiguity.
βœ” Clear timelines with milestones β€” To reduce disputes over delay.
βœ” Risk allocation matrix β€” Define events triggering contractor vs owner risk.
βœ” Insurance requirements β€” Including environmental and hull insurance.
βœ” Explicit termination terms, including compensation model
βœ” Choice of Law & ARB Clause β€” Often ICC/LCIA arbitration with seat in neutral territory.

πŸ“Œ 7. Summary: How These Disputes Get Resolved

Courts & tribunals assess:

Contractual language

Performance evidence

Applicable law

Risk allocation

Proven damages

Outcomes may include:

βœ… Damages for breach
βœ… Specific performance orders
βœ… Arbitral awards
βœ… Adjustment of liquidated damages
βœ… Compensation for demobilization and loss of profit

LEAVE A COMMENT