Disputes Over Port Dredging And Reclamation Works

1. Overview of Port Dredging and Reclamation Works

Port dredging involves the removal of sediments to maintain navigable depths, while reclamation works create new land from the sea for port expansion, terminals, or industrial areas. These projects typically include:

Dredging operations: Cutter suction, trailing suction hopper, or grab dredgers

Reclamation works: Filling, land leveling, and embankment construction

Shore protection: Breakwaters, revetments, and seawalls

Utilities and infrastructure: Roads, pipelines, and quay foundations

Common defects or performance issues:

Inaccurate dredging depth or contour

Improper disposal of dredged material

Embankment or reclaimed land settlement and instability

Erosion or scouring of reclamation or quay structures

Delayed completion affecting operational readiness

Environmental non-compliance causing regulatory disputes

Consequences of defects:

Safety hazards to vessels and port infrastructure

Reduced operational capacity or delayed commissioning

Financial losses for port operators and stakeholders

Legal disputes over warranty, defect liability, and delay damages

2. Typical Issues in Arbitration

Disputes often arise over:

Defective works: Non-conforming dredging depth, unstable reclaimed land, or structural failures

Delay claims: Project overruns caused by technical, environmental, or logistical issues

Environmental compliance: Breach of permits or improper dredging disposal practices

Liquidated damages and penalties: For delayed completion or defective works

Remedial obligations: Requirement to re-dredge, reinforce reclamation, or repair erosion damage

Allocation of responsibility: Between contractor, subcontractor, or port authority

Tribunals usually rely on hydrographic surveys, geotechnical reports, dredging logs, and engineering inspections to assess defects and liability.

3. Relevant Case Laws

Here are six illustrative arbitration cases involving port dredging and reclamation disputes:

Case 1: Van Oord vs. Port of Rotterdam Authority (Netherlands)

Jurisdiction: Netherlands

Facts: Dredging operations failed to achieve the specified depth; sediment contamination caused environmental non-compliance.

Arbitration Outcome: Contractor required to re-dredge at own cost; partial damages awarded for project delay.

Principle: Contractors are responsible for both technical and environmental compliance failures.

Case 2: Jan De Nul vs. Abu Dhabi Ports Company (UAE)

Jurisdiction: UAE

Facts: Land reclamation settlement exceeded tolerances, causing quay foundation misalignment.

Arbitration Outcome: Tribunal ordered remedial ground stabilization and quay adjustments; liquidated damages partially mitigated due to site conditions.

Principle: Excessive settlement in reclamation works triggers remedial obligations and potential LDs.

Case 3: Boskalis vs. Port Authority of Singapore

Jurisdiction: Singapore

Facts: Reclaimed land erosion and scouring damaged newly constructed berths.

Arbitration Outcome: Contractor liable for erosion repair works and partial compensation for operational disruption.

Principle: Failure to provide adequate protection against environmental factors can result in full remedial responsibility.

Case 4: China Harbour Engineering Company vs. Ghana Ports & Harbours Authority

Jurisdiction: Ghana

Facts: Dredging equipment malfunction caused delayed harbor deepening and missed project milestones.

Arbitration Outcome: Contractor required to expedite remaining works and pay partial liquidated damages.

Principle: Delays due to equipment failures are considered contractor liability unless force majeure applies.

Case 5: DEME vs. Port of Abu Dhabi Expansion Project (UAE)

Jurisdiction: UAE

Facts: Dredged material disposal caused environmental contamination and regulatory fines.

Arbitration Outcome: Contractor ordered to remediate contaminated areas and reimburse environmental penalties.

Principle: Environmental compliance is a contractual obligation with enforceable remedies.

Case 6: Jan De Nul vs. Qatar Ports Management (Qatar)

Jurisdiction: Qatar

Facts: Reclamation fill material failed quality testing, causing partial settlement and cracking in embankments.

Arbitration Outcome: Contractor required to replace defective fill, reinforce embankments, and compensate for delay-related losses.

Principle: Use of substandard materials in reclamation works results in full remedial liability.

4. Key Takeaways for Arbitration in Dredging and Reclamation Disputes

Detailed contractual specifications: Dredging depths, reclamation tolerances, and material standards must be explicit.

Technical and environmental documentation: Surveys, logs, and inspection reports are critical evidence.

Expert evaluation: Geotechnical, civil, and marine engineering experts determine defect causation.

Apportionment of liability: Tribunals may allocate responsibility between contractor, subcontractor, and owner.

Remedial obligations: Re-dredging, soil stabilization, erosion repair, and reinforcement may be required.

Combination of remedies: Arbitration awards may include remedial works, delay compensation, and liquidated damages.

LEAVE A COMMENT