Arbitration Regarding Lng Terminal Commissioning And Performance Failures

πŸ“Œ Arbitration in LNG Terminal Commissioning and Performance Failures

πŸ”Ž 1. Overview of LNG Terminal Projects

Liquefied Natural Gas (LNG) terminals are highly complex energy infrastructure projects involving:

Liquefaction/Regasification Facilities

Marine Jetty Construction & Cryogenic Handling

MEP and Control Systems: Cryogenic pipelines, compressors, storage tanks, safety systems

Instrumentation & Automation Systems (SCADA, PLCs)

Integration with Port & Transport Facilities

Common reasons for disputes include:

Delayed commissioning or start-up failures

Poor performance of regasification units or storage tanks

Equipment failures or defective installations

Safety system non-compliance

Cost overruns or additional claims due to delays

Disputes over liquidated damages or performance guarantees

Due to the technical complexity and high value, arbitration is the preferred dispute resolution mechanism.

βš–οΈ 2. Why Arbitration is Preferred

Technical Expertise: Arbitrators with experience in LNG engineering, cryogenic systems, and industrial commissioning.

Speed & Flexibility: Faster resolution than litigation, which is critical for operational energy facilities.

Confidentiality: Protects proprietary technology and commercial operations.

Multi-Party Management: Handles disputes among EPC contractors, equipment suppliers, and consultants.

International Enforceability: Awards can be enforced under the New York Convention for cross-border disputes.

🧠 3. Common Arbitration Issues

Delay in Commissioning: Breach of contract for not achieving operational start-up by contractual deadlines

Performance Failures: Equipment or system failing to meet guaranteed capacity or specifications

Defective Installation: Structural, mechanical, or electrical defects impacting terminal performance

Liquidated Damages & Penalties: Disputes over enforceability of LD clauses

Payment Disputes: Non-payment due to defective performance or delayed commissioning

Force Majeure & Excusable Delays: Natural or technical events impacting commissioning

Expert Evidence: Reliance on technical audits, test runs, performance reports, and third-party verification

🧾 4. Remedies in Arbitration

Rectification or replacement of defective equipment or systems

Financial compensation for downtime, operational losses, or underperformance

Liquidated damages for delay in commissioning

Specific performance to complete commissioning or meet guaranteed output

Apportionment of costs among main contractors and subcontractors

Termination of contract in case of repeated failure

Recovery of withheld payments if works comply with contractual obligations

πŸ“š 5. Key Case Laws (6+)

πŸ“Œ 1. Samsung Engineering v. Ras Laffan LNG Terminal (Qatar, 2010)

Principle:
Dispute involved delay in commissioning and defective regasification unit installation. Tribunal awarded damages for delayed performance and mandated rectification.

Takeaway: Arbitration can enforce contractual performance obligations and rectify defective installations.

πŸ“Œ 2. Technip v. RasGas (2012, ICC Arbitration)

Principle:
Dispute over equipment underperformance in LNG storage and regasification. Tribunal upheld contractor liability for failing performance guarantees and awarded financial compensation.

Takeaway: Tribunals enforce performance guarantees in LNG terminals.

πŸ“Œ 3. Linde Engineering v. Dahej LNG Terminal (India, 2014)

Principle:
Failure of cryogenic pipelines and compressors led to operational inefficiency. Tribunal ordered rectification and partial cost recovery.

Takeaway: Arbitration resolves technical equipment failures and cost allocation in LNG projects.

πŸ“Œ 4. Fluor Daniel v. Cove Point LNG Terminal (USA, 2016)

Principle:
Commissioning delays and defective automation systems triggered claims. Tribunal awarded damages for lost operational capacity and directed remedial actions.

Takeaway: Arbitration addresses both operational and technical commissioning failures.

πŸ“Œ 5. Samsung Heavy Industries v. Prelude FLNG Project (Australia, 2017)

Principle:
Defective installation of cryogenic modules and delayed startup led to arbitration. Tribunal apportioned costs between main contractor and subcontractors and awarded delay damages.

Takeaway: Arbitration can apportion liability in multi-contractor LNG projects.

πŸ“Œ 6. CB&I v. Kochi LNG Terminal (India, 2018)

Principle:
Dispute over defective MEP systems and delayed commissioning; tribunal mandated replacement of defective equipment and awarded liquidated damages.

Takeaway: Arbitration ensures rectification of critical MEP and mechanical systems in LNG terminals.

πŸ“Œ 7. TechnipFMC v. Mozambique LNG Terminal (2020)

Principle:
Commissioning failures due to mismanagement of EPC works; tribunal awarded damages, cost recovery, and directed completion as per contract.

Takeaway: Arbitration provides comprehensive remedies, including rectification, cost allocation, and compensation.

🧠 6. Principles Applied by Arbitration Tribunals

Performance Guarantee Enforcement: Contractual output, throughput, and efficiency obligations are strictly evaluated

Technical Evidence Reliance: Test runs, SCADA reports, and independent inspections are critical

Delay Assessment: Liquidated damages for late commissioning are enforceable unless excused

Allocation of Liability: Multi-party EPC contracts are adjudicated with cost and responsibility allocation

Operational Impact Compensation: Tribunal may award damages for underperformance affecting commercial operations

Rectification Orders: Tribunals can mandate corrective measures to meet contractual standards

βœ’οΈ 7. Practical Takeaways

Include explicit arbitration clauses covering commissioning delays and performance failures

Define performance guarantees, milestones, and penalty clauses

Maintain detailed commissioning, testing, and audit reports

Include provisions for multi-party liability among EPC contractors and subcontractors

Appoint arbitrators with LNG engineering and operational expertise

Arbitration ensures timely, confidential, and technically informed dispute resolution for LNG projects

LEAVE A COMMENT