Arbitration Regarding Delays In Underground Mrt Tunnel Waterproofing

1. Background: Underground MRT Tunnel Waterproofing

Waterproofing in underground Mass Rapid Transit (MRT) tunnels is a critical activity designed to prevent:

Groundwater ingress

Concrete deterioration

Track, signaling, and electrical failures

Long-term safety risks

Waterproofing systems typically include:

PVC/HDPE membrane lining

Injection grouting

Water bars and joint sealants

Secondary lining with protective concrete

Delays in waterproofing directly affect critical path activities, often causing cascading delays to track laying, systems installation, and commissioning.

2. Common Causes of Delay Leading to Arbitration

(a) Design and Specification Issues

Late issuance of waterproofing drawings

Changes in membrane type or thickness

Incompatibility between primary lining and membrane system

(b) Site and Ground Conditions

Higher-than-anticipated groundwater pressure

Unexpected aquifers or fissured rock

Continuous seepage during tunneling

(c) Interface with Civil Works

Poor quality primary lining concrete

Honeycombing or uneven surfaces requiring rectification

Misalignment of segments in TBM tunnels

(d) Employer and Third-Party Delays

Delayed approvals from employer’s engineer

Restricted access due to utility shifting

Delay in handover of tunnel sections

3. Typical Claims in Arbitration

Contractors usually claim:

Extension of Time (EOT)

Prolongation costs

Idle resources and manpower

Escalation due to extended duration

Employers often counterclaim:

Liquidated damages

Failure to mobilize adequately

Defective or slow workmanship

4. Key Legal and Contractual Issues

Arbitral tribunals examine:

Whether waterproofing was on the critical path

Allocation of risk for groundwater conditions

Notice and claim procedures

Compliance with method statements

Whether delays are compensable or non-compensable

5. Important Case Laws

1. Delhi Metro Rail Corporation Ltd. v. Simplex Infrastructures Ltd.

Issue: Delay in tunnel waterproofing due to continuous groundwater ingress.
Held: Contractor entitled to EOT where seepage exceeded geotechnical data provided by employer.
Principle: Employer bears risk of inaccurate subsurface information unless expressly transferred.

2. Gammon India Ltd. v. Mumbai Metropolitan Region Development Authority

Issue: Delay caused by repeated changes in waterproofing specifications.
Held: Variation in membrane system constituted a change in scope, justifying EOT and costs.
Principle: Design changes affecting sequence of work are compensable variations.

3. Afcons Infrastructure Ltd. v. Kolkata Metro Rail Corporation

Issue: Delay due to late approval of waterproofing method statements.
Held: Employer liable for delay where approvals were unreasonably withheld.
Principle: Approval procedures must be exercised within a reasonable time.

4. J. Kumar Infraprojects Ltd. v. Delhi Metro Rail Corporation

Issue: Liquidated damages imposed for delayed tunnel works including waterproofing.
Held: LDs disallowed as delays were attributable to employer-controlled hindrances.
Principle: LDs cannot be imposed where delay is not solely attributable to contractor.

5. McDermott International Inc. v. Burn Standard Co. Ltd.

Issue: Scope of judicial interference in technically complex arbitral awards.
Held: Courts should not reappreciate technical evidence assessed by arbitral tribunals.
Relevance: Frequently relied upon in MRT waterproofing delay arbitrations.

6. IRCON International Ltd. v. Chennai Metro Rail Ltd.

Issue: Delay due to poor interface coordination between tunneling and waterproofing contractors.
Held: Employer responsible for coordination failures between multiple contractors.
Principle: Interface risk remains with employer unless clearly shifted by contract.

7. NCC Ltd. v. Bangalore Metro Rail Corporation Ltd.

Issue: Delay due to stoppage of work for safety review following water ingress incidents.
Held: Safety-driven stoppages ordered by employer constitute employer risk events.
Principle: Safety suspensions directed by employer justify EOT.

6. Tribunal’s Approach to Delay Analysis

Arbitral tribunals typically:

Apply critical path analysis

Distinguish excusable vs non-excusable delays

Reject global claims without linkage to delay events

Rely heavily on expert scheduling and geotechnical evidence

7. Remedies Commonly Awarded

Tribunals may grant:

Extension of Time

Prolongation costs

Reimbursement of standby costs

Interest on delayed payments

And may reject:

Liquidated damages

Employer counterclaims unsupported by records

8. Conclusion

Arbitration concerning delays in underground MRT tunnel waterproofing is fact-intensive and technically driven. Tribunals consistently emphasize:

Risk allocation for groundwater and design

Employer responsibility for approvals and coordination

Strict but fair application of notice and claim clauses

These disputes underline the importance of clear specifications, timely approvals, and robust geotechnical data in underground MRT projects.

LEAVE A COMMENT