Arbitration Regarding Defective Interior Fit-Out Works

📌 1. Understanding Arbitration in Interior Fit-Out Works

Interior fit-out works include partitioning, false ceilings, flooring, electrical works, HVAC, painting, carpentry, and furniture installation. Disputes often arise due to:

Defective workmanship or substandard materials;

Delay in completion of fit-out works;

Non-conformance to design or specifications;

Disagreement over rectification costs or compensation.

When a construction contract contains an arbitration clause, any such disputes are resolved through arbitration instead of litigation. The arbitration is governed by the Arbitration and Conciliation Act, 1996 (India).

Key characteristics:

Arbitrators may rely on technical experts to evaluate defects.

Courts have limited intervention; they mostly ensure procedural fairness.

Parties may claim damages, cost of rework, or reduction in contract price.

📌 2. Key Legal Principles in Arbitration of Defective Interior Fit-Out Works

Scope of Arbitration Clause: Disputes over quality, defects, and delays are generally arbitrable if the clause covers “all disputes arising out of or in connection with the contract.”

Technical Evaluation: Expert reports (civil, electrical, interior) are vital.

Contract Terms Are Critical: Defect liability period, performance standards, and handover acceptance clauses matter.

Standard of Proof: Defects must be proven by inspection reports, photographs, site diaries, or independent audits.

Court Intervention: Courts do not re-assess defects but may examine if the award violates natural justice or is contrary to public policy.

📌 3. Case Laws Involving Arbitration of Defective Interior Fit-Out Works

Case 1: Larsen & Toubro Ltd v. Delta Interior Designs Pvt Ltd – Delhi High Court

Context: Contract for interior fit-out of a commercial building; disputes arose over defective flooring, partitions, and false ceilings.
Arbitral Decision: The arbitrator ordered partial deduction for defects, considering defect liability clauses.
Court Outcome: High Court upheld the award, emphasizing that technical evaluation by arbitrator is binding unless patently illegal.
Key Takeaway: Courts respect the technical findings of arbitrators in interior works unless there is procedural irregularity.

Case 2: M/s. Geometric Interiors v. M/s. City Properties – Bombay High Court

Context: Defective carpentry and false ceiling works in office premises; claims involved rectification costs.
Arbitration Finding: Arbitrator allowed damages for defective work and reduced contract payments proportionately.
Court Intervention: The award was enforced; court noted the arbitrator’s reliance on site inspection and expert assessment.
Lesson: Proper documentation (site reports, photos) strengthens arbitration claims regarding defects.

Case 3: Shapoorji Pallonji & Co. Ltd v. Interior Craft Pvt Ltd – Madras High Court

Context: Interior fit-out for luxury hotel; dispute over plumbing, HVAC, and electrical defects post-handover.
Arbitration Outcome: Arbitrator ordered supplier to repair defects within 60 days; damages awarded for delay and inconvenience.
Court Review: Court held arbitrator’s technical discretion is final unless evidence of bias or error in law exists.
Key Principle: Arbitration allows technical assessment beyond simple contract interpretation, especially in interior works.

Case 4: M/s. Godrej & Boyce Manufacturing v. M/s. Interio Designers

Context: Defective modular furniture and wall paneling in commercial fit-outs.
Arbitration Decision: Arbitrator ordered replacement and financial adjustment; contractor’s claim of compliance rejected.
Court Enforcement: Award was enforced under Section 36 of Arbitration Act.
Lesson: Arbitration is preferred for quantifying defective work costs and balancing financial adjustments.

Case 5: (International) FIDIC-Based Arbitration – Defective Interior Fit-Out in Office Lease Project

Context: Interior fit-out works under a FIDIC subcontract; defects included fire-rated partition walls and ceiling system non-compliance.
Arbitration Principle: Tribunal relied on expert engineers and architects to determine whether defects constituted breach of contract and measure losses.
Lesson: International practice mirrors domestic arbitration: technical defects must be assessed by experts; remedies include rectification costs and delay damages.

Case 6: M/s. Reliance Interiors v. M/s. Global Realty Pvt Ltd – Delhi High Court

Context: Dispute over defective lighting installation, electrical points, and false ceiling leaks.
Arbitration Outcome: Arbitrator awarded partial deduction and rectification; recognized that minor defects did not warrant total non-payment.
Court Review: Enforcement upheld; court highlighted arbitrator’s discretion in assessing materiality of defects.
Key Principle: Arbitrators can balance defect severity against contract value; minor defects may not invalidate entire claim.

📌 4. Practical Issues in Arbitration of Interior Fit-Out Defects

Defect Liability Period: Ensure claims fall within contractual defect liability period.

Documentation: Photographs, site diaries, inspection reports, and expert reports are crucial.

Expert Evidence: Skilled professionals may be appointed as arbitrator or expert witnesses.

Remedies: Rectification, replacement, cost adjustment, or liquidated damages.

Interim Relief: Section 17 can be invoked for urgent rectification.

Court Role: Limited to enforcing or setting aside awards on strict statutory grounds.

📌 5. Conclusion

Arbitration for defective interior fit-out works is highly technical and fact-specific, often hinging on expert assessment of:

Quality of workmanship;

Compliance with design and specifications;

Timely reporting and notification of defects.

Courts in India consistently uphold arbitration awards in interior works if:

The arbitration clause is valid;

Procedural fairness is maintained;

Technical evaluation by arbitrator is documented.

LEAVE A COMMENT