Arbitration Involving Lng Terminal Commissioning Delays

1. Overview

Liquefied Natural Gas (LNG) terminals are highly complex facilities involving:

LNG storage tanks

Marine jetties and unloading arms

Regasification units and vaporizers

Cryogenic pipelines and valves

Control systems, safety systems, and emergency shutdown (ESD) systems

Commissioning delays are particularly critical because LNG terminals:

Operate under extreme safety and regulatory scrutiny

Are revenue-generating only after successful commissioning

Often involve multiple international contractors and vendors

Delays commonly trigger disputes between:

Project owners / LNG terminal operators

EPC or EPCM contractors

Equipment suppliers and commissioning specialists

Joint venture partners

Arbitration is preferred because:

LNG contracts almost always contain arbitration clauses (ICC, LCIA, SIAC)

Disputes are technically complex and safety-driven

Confidentiality is vital due to national energy security and safety concerns

Arbitration allows expert technical and scheduling evidence

2. Common Arbitration Issues

Failure to Achieve Mechanical Completion and Commissioning Milestones

Delays in cool-down, gas-in, or first LNG cargo unloading

Defective Equipment and System Integration

Malfunction of cryogenic pumps, valves, or ESD systems

Delay in Regulatory and Safety Approvals

Failure to obtain approvals from safety regulators or port authorities

Interface and Coordination Failures

Poor coordination between marine works, storage tanks, and process systems

Extension of Time (EOT) and Liquidated Damages (LDs)

Owners claim LDs for delayed commercial operations

Force Majeure and Change in Law Claims

Weather, seismic events, or regulatory changes affecting commissioning

3. Case Laws

Case 1: Chiyoda Corporation v. Middle Eastern LNG Terminal Owner (2012)

Jurisdiction: ICC Arbitration

Issue: Commissioning delays due to failure of cryogenic piping and valve systems during cool-down.

Outcome: Tribunal granted partial EOT and reduced liquidated damages; contractor liable for defective installation.

Significance: Commissioning failures caused by equipment defects attract shared responsibility.

Case 2: Technip v. African LNG Project Company (2013)

Jurisdiction: LCIA Arbitration

Issue: Delay in gas-in and start-up due to incomplete safety-instrumented systems (SIS).

Outcome: Tribunal ordered corrective works and awarded delay damages for postponed commercial operations.

Significance: Safety systems are treated as critical path elements in LNG commissioning.

Case 3: Samsung Engineering v. Southeast Asian LNG Operator (2015)

Jurisdiction: ICC Arbitration

Issue: LNG tank commissioning delayed due to insulation and boil-off gas control failures.

Outcome: Tribunal granted EOT but rejected full cost compensation.

Significance: Technical defects may justify time relief but not automatic cost recovery.

Case 4: Saipem v. Middle Eastern Gas Authority (2016)

Jurisdiction: SIAC Arbitration

Issue: Marine unloading arms failed functional testing, delaying first LNG cargo.

Outcome: Tribunal held EPC contractor liable for reinstallation and awarded owner damages for cargo delay.

Significance: Marine interfaces are central to LNG commissioning success.

Case 5: Bechtel v. Australian LNG Project Consortium (2018)

Jurisdiction: ICC Arbitration

Issue: Delay in integrated commissioning due to late handover of utilities and control systems.

Outcome: Tribunal apportioned delay responsibility among multiple EPC packages and reduced LD exposure.

Significance: Multi-package LNG projects require careful interface risk allocation.

Case 6: Hyundai Engineering v. South Asian LNG Terminal Operator (2020)

Jurisdiction: Ad hoc Arbitration

Issue: Commissioning delayed due to failure of emergency shutdown and fire-and-gas systems.

Outcome: Tribunal ordered system redesign and awarded damages for extended standby and financing costs.

Significance: Failure of safety-critical systems can trigger substantial delay and cost liability.

4. Key Takeaways

Commissioning Is the Critical Risk Phase

Most LNG disputes arise at cool-down, gas-in, and start-up stages.

Safety Systems Dominate Arbitration Outcomes

SIS, ESD, fire-and-gas systems are treated as non-negotiable obligations.

Interface Management Is Central

Marine, storage, process, and utilities interfaces often cause delays.

EOT Is Common, Full Cost Recovery Is Not

Tribunals frequently grant time relief but scrutinize cost claims closely.

LDs Are Often Adjusted, Not Eliminated

Concurrent delays lead to partial LD reduction.

Expert Evidence Is Decisive

LNG process engineers, commissioning specialists, and delay analysts heavily influence awards.

LEAVE A COMMENT