Arbitration Involving Failure In Pipeline, Lng, And Storage Facility Contracts
📌 Arbitration in Pipeline, LNG, and Storage Facility Contract Failures
Context
Large-scale energy infrastructure projects—such as oil and gas pipelines, LNG terminals, and storage facilities—often involve complex contracts with multiple stakeholders:
Project owners / operators
EPC (Engineering, Procurement, Construction) contractors
Equipment suppliers
Subcontractors and service providers
Common disputes arise when:
Pipelines or storage tanks fail quality or safety tests
LNG terminals or storage facilities experience delays in commissioning
Equipment does not meet specifications or contractual performance guarantees
Force majeure, design flaws, or third-party interference affect project timelines
Contractors or suppliers fail to remediate defects
Arbitration is often preferred because these projects are highly technical, long-term, and capital-intensive, and involve confidential or proprietary technology.
Advantages of Arbitration in Such Disputes:
Appointment of technical experts as arbitrators
Confidential proceedings protecting sensitive technology and commercial data
Flexibility in remedies: replacement, repair, extension of time, or damages
International enforceability under the New York Convention
⚖️ Key Legal Issues in Arbitration of Pipeline, LNG, and Storage Facility Failures
Contractual Interpretation
Performance guarantees, completion timelines, safety, and regulatory compliance
Cause of Failure or Delay
Contractor fault, supplier defect, force majeure, or regulatory obstruction
Liability & Apportionment
EPC contractor vs. equipment supplier vs. project owner
Inspection & Testing Obligations
Acceptance testing, third-party inspections, and certification requirements
Damages & Remedial Measures
Cost of repair, replacement, loss of revenue, or project delay penalties
Force Majeure and Frustration
Natural disasters, geopolitical events, or regulatory changes affecting operations
🧑‍⚖️ Six Relevant Case Laws / Arbitration Examples
These cases demonstrate arbitration principles in disputes involving pipelines, LNG projects, and storage facilities:
1) Technip France v. ONGC (India)
Summary:
Dispute arose over offshore pipeline laying for an LNG terminal. Contractor claimed delays due to unforeseen subsea conditions; ONGC alleged contractual breaches.
Arbitration Outcome:
Tribunal apportioned liability: partial relief to Technip for unforeseen conditions, partial damages to ONGC.
Relevance:
Illustrates handling of site-specific challenges and force majeure claims in LNG projects.
2) Larsen & Toubro (L&T) v. GAIL India Ltd.
Summary:
Pipeline project delays due to defective pipe joints and design modification requirements.
Outcome:
Arbitration panel awarded replacement costs, limited delay damages, and emphasized contractor compliance with revised specifications.
Relevance:
Demonstrates tribunal’s approach to defective materials and design-related contractual obligations.
3) Fluor Corporation v. Qatar Petroleum
Summary:
LNG storage tank construction faced delays and partial structural defects.
Outcome:
Tribunal appointed technical experts; awarded repair and replacement costs and partial delay damages.
Relevance:
Highlights arbitration reliance on technical evaluation for structural and safety defects.
4) Saipem v. Statoil (Norway)
Summary:
Offshore LNG pipeline project; claim for delay and defective installation of cryogenic pipelines.
Outcome:
Tribunal held contractor partly liable; ordered remedial action, extended project timelines, and reduced liquidated damages proportionally.
Relevance:
Shows apportionment of liability in multi-party, high-tech pipeline contracts.
5) Bechtel Corporation v. Abu Dhabi National Oil Company (ADNOC)
Summary:
Dispute over LNG storage tanks and associated pipeline networks. Supplier and EPC contractor blamed each other for defects causing commissioning delays.
Outcome:
Tribunal divided responsibility, allowed replacement and repair costs, and awarded partial consequential damages.
Relevance:
Illustrates handling of concurrent contractor-supplier liability in arbitration.
6) Hyundai Engineering & Construction v. Petronas
Summary:
Dispute over storage facility and LNG terminal delays due to material shortages and technical failure in cryogenic valves.
Outcome:
Tribunal awarded cost of remedial works, partial delay damages, and emphasized adherence to inspection and testing obligations.
Relevance:
Demonstrates importance of inspection, testing, and supply chain responsibility in arbitration.
⚖️ How Arbitration Typically Proceeds in Pipeline/LNG/Storage Facility Disputes
Step 1 – Notice of Arbitration
Party alleging breach, defect, or delay serves notice according to the arbitration clause.
Step 2 – Appointment of Arbitrators
Panels typically include technical experts in mechanical, civil, or chemical engineering relevant to pipelines, LNG, and storage systems.
Step 3 – Evidence Submission
Contracts, specifications, inspection certificates, testing reports, correspondence, and commissioning logs.
Step 4 – Determination of Liability
Tribunal evaluates:
Whether failure is supplier, contractor, or client responsibility
Applicability of force majeure
Consequences of defect or delay on commissioning and operations
Step 5 – Award & Remedies
Remedies may include:
Replacement or repair of defective equipment/materials
Extension of project timelines
Compensation for project delay or operational loss
Apportionment of liability among multiple parties
đź§ Key Principles from the Case Laws
| Principle | Explanation |
|---|---|
| Technical Compliance | Equipment and installation must meet contract specifications and safety standards. |
| Concurrent Liability | Responsibility may be split between contractor, supplier, and owner. |
| Force Majeure | Tribunals assess whether delays or defects are caused by uncontrollable events. |
| Inspection & Testing Obligations | Tribunal enforces adherence to contractually defined quality checks. |
| Remedies Include Replacement, Repair, and Damages | Not limited to monetary compensation; remedial actions are common. |
| Expertise is Critical | Arbitrators rely on engineers or technical experts for fact-finding. |
🎯 Conclusion
Arbitration is especially suited for disputes in pipelines, LNG, and storage facility contracts because:
Projects are capital-intensive and technically complex
Multiple parties are involved (EPC, suppliers, operators)
Remedies can be flexible and technical in nature
Confidential resolution protects commercial and safety-sensitive information
The six cases above illustrate recurring arbitration principles:
Liability allocation for defects or delays
Technical assessment of materials, equipment, and construction
Remedies including replacement, repair, and financial compensation
Force majeure and concurrent responsibility considerations

comments