Arbitration Involving Design-Build And Epc Contract Disputes

I. Introduction: Design-Build and EPC Contracts

Design-Build and EPC contracts are delivery models in which a single contractor assumes responsibility for design, procurement, construction, testing, and commissioning, often on a turnkey basis.

They are widely used in:

Power plants, renewables, oil & gas

Infrastructure (roads, rail, airports)

Industrial facilities

Large commercial developments

Because DB/EPC projects are high-value, technically complex, and frequently cross-border, arbitration is the preferred dispute-resolution mechanism.

II. Typical Causes of Arbitration in DB and EPC Contracts

1. Design Defects and Performance Failures

Failure to meet output, capacity, or efficiency guarantees

Non-compliance with employer’s requirements

2. Delay and Liquidated Damages (LD)

Missed milestones or Commercial Operation Date (COD)

Disputes over entitlement to extensions of time (EOT)

3. Scope Creep and Variations

Whether changes fall within original scope

Pricing and time impacts of variations

4. Fitness for Purpose vs Skill and Care

Conflict between “fitness for purpose” obligations and professional standards

5. Force Majeure and Change in Law

Regulatory changes

Supply chain disruptions

6. Termination and Step-In Rights

Employer termination for default

Contractor termination for non-payment

III. Core Legal Issues Arbitrators Examine

Arbitral tribunals typically focus on:

Contractual risk allocation

Hierarchy of contract documents

Interpretation of performance guarantees

Causation of delay (critical path)

Interaction between LD and damages

Limitation and exclusion of liability

IV. Case Laws Relevant to DB and EPC Arbitration

While most EPC arbitrations remain confidential, tribunals consistently rely on construction, infrastructure, and commercial precedents.

Case 1: MT Højgaard A/S v. E.ON Climate & Renewables UK Ltd

(UK Supreme Court)

Relevance

EPC contract involving defective foundation design

Key Holding

Fitness-for-purpose obligations override compliance with industry standards

Application

EPC contractors are liable even if they follow employer-approved designs

Case 2: Triple Point Technology Inc v. PTT Public Company Ltd

(UK Supreme Court)

Relevance

Liquidated damages in EPC-style contracts

Key Principle

LD clauses apply until termination unless contract states otherwise

Application

Frequently cited in EPC delay arbitrations

Case 3: Alstom Power Ltd v. Yokogawa India Ltd

(Supreme Court of India)

Relevance

Performance testing and acceptance under EPC contracts

Key Holding

Contractually agreed performance tests are binding

Application

Output and efficiency tests in EPC power projects

Case 4: ONGC v. Saw Pipes Ltd

(Supreme Court of India)

Relevance

LD and failure to meet technical specifications

Key Principle

LD enforceable where contract clearly specifies standards

Application

Underperformance automatically triggers LD in EPC contracts

Case 5: United States v. Spearin

(US Supreme Court – Spearin Doctrine)

Relevance

Allocation of design risk

Key Holding

Employer warrants adequacy of designs it provides

Application

Used where employer’s requirements are defective in DB/EPC projects

Case 6: Walter Lilly & Company Ltd v. Mackay

(UK Technology and Construction Court)

Relevance

Delay and design responsibility

Key Holding

Contractor entitled to EOT for employer-caused delays

Application

Interface issues between employer’s requirements and contractor design

Case 7: ICC Case No. 2508 (Turnkey Power Plant Dispute)

Relevance

Failure to meet guaranteed output under EPC contract

Key Findings

Contractor liable for system integration failures

Legal Principle

EPC responsibility is holistic, not component-based

V. Remedies Commonly Awarded in DB/EPC Arbitrations

Arbitral tribunals may grant:

Liquidated damages

General damages for delay or defect

Extension of time

Replacement or rectification costs

Termination compensation

Performance bond calls

Punitive damages are rare unless fraud is proven.

VI. Drafting Lessons from Arbitration Practice

Key takeaways:

Define performance guarantees precisely

Clarify fitness-for-purpose obligations

Set clear LD caps and triggers

Establish document hierarchy

Address change-in-law mechanisms

Provide expert determination for technical disputes

VII. Conclusion

Arbitration involving DB and EPC contracts is contract-centric, evidence-heavy, and technically complex. Tribunals consistently hold that:

EPC contractors bear comprehensive risk

Fitness-for-purpose clauses impose strict liability

LD clauses are enforceable if clearly drafted

Design responsibility must be explicitly allocated

As infrastructure and energy projects continue to grow globally, DB and EPC arbitration remains one of the most developed and influential areas of international construction arbitration.

LEAVE A COMMENT