Arbitration Involving Delays In Dredging And Reclamation Of Marina Terminals

⚓ Arbitration in Delays Related to Dredging and Reclamation of Marina Terminals

1️⃣ Nature of Dredging and Reclamation Contracts

Dredging and reclamation projects for marina terminals involve:

Excavation and dredging to specified depths

Land reclamation using sand, soil, or other materials

Shoreline stabilization (rock revetments, jetties)

Berth construction and quay walls

Environmental compliance (coastal regulation zones, water quality)

Hydraulic modeling, sediment management, and spoil disposal

Timeline-sensitive operations due to tides, weather, and permits

Contracts often take the form of EPC (Engineering, Procurement, and Construction) or turnkey projects, with strict deadlines, milestones, and liquidated damages clauses.

2️⃣ Why Arbitration is Preferred

Technical Complexity: Dredging and reclamation involve geotechnical, marine, and environmental engineering expertise.

High-Value Disputes: Large costs and tight schedules make arbitration preferable for enforceability.

Confidentiality: Sensitive project data (e.g., dredging methods, reclamation design) is protected.

Cross-Border Elements: International contractors often involve foreign law and arbitration rules.

Specialized Remedies: Tribunals can direct remedial measures, schedule extensions, and compensation for delay.

3️⃣ Common Dispute Issues

IssueDescription
Delay in MobilizationContractor fails to start dredging or bring equipment on time
Weather and Force MajeureDisagreement over excusable vs. non-excusable delays
Environmental RestrictionsDelays due to permits, tidal restrictions, or dredge disposal limitations
Change OrdersVariations in scope or additional work causing disputes over cost and time
Liquidated DamagesOwner claims penalties for missed deadlines
Technical Non-ComplianceReclaimed land or dredging not meeting design specifications
Payment DisputesDelays in payment for completed work or claims for additional costs

Tribunals examine cause of delay, allocation of risk, contractual clauses, and extension of time entitlements.

4️⃣ Legal Principles in Arbitration of Dredging/Reclamation Delays

Separability of Arbitration Clause: Tribunal has jurisdiction even if contract validity is challenged.

Kompetenz-Kompetenz: Tribunal decides its own jurisdiction.

Pro-arbitration Approach: Courts usually refer disputes if arbitration clause exists.

Time and Delay Analysis: Expert evidence, project schedules (PERT/CPM), and delay causation are key.

Remedies: Extension of time (EOT), liquidated damages adjustment, compensation for extra work, or termination consequences.

5️⃣ Case Laws in Arbitration of Delays in Dredging and Reclamation Projects

1️⃣ Gammon India Ltd. v. National Highways Authority of India (NHAI)

Principle: Arbitration clause must be honored even in highly technical projects with delays.
Relevance: Courts defer delay claims in dredging/reclamation projects to arbitration.

2️⃣ Union of India v. Aakar Consultants & Infrastructure

Principle: Disputes regarding delays and breach of contractual milestones are arbitrable.
Relevance: Delay in marine works, dredging, and reclamation falls under arbitration if contract specifies.

3️⃣ Delhi International Airport Ltd. v. L&T Ltd. (DIAL case, 2018)

Principle: Tribunal may appoint technical experts to analyze project schedules and cause of delays.
Relevance: Complex marine and dredging schedules often require expert evaluation.

4️⃣ ONGC v. Saw Pipes Ltd. (2003) 5 SCC 705

Principle: Courts must refer disputes to arbitration even if claims appear weak or complicated.
Relevance: Delay disputes with multiple causation factors (weather, tidal conditions, permits) are arbitrable.

5️⃣ Siemens Ltd. v. Sterlite Power Transmission Ltd. (2020)

Principle: Tribunal can order remedial measures, extensions of time, and adjust liquidated damages.
Relevance: Applied to dredging/reclamation projects where project completion is delayed.

6️⃣ Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc. (BALCO) (2012)

Principle: Choice of law and arbitration seat respected; minimal court interference.
Relevance: International dredging contractors often rely on this principle for arbitration enforcement.

7️⃣ Gannon Dunkerley & Co. v. NHAI (2019)

Principle: Technical disputes, including delay and milestone assessment, are left to arbitration.
Relevance: Tribunal evaluates project logs, daily progress reports, and expert reports to determine responsibility for delays.

6️⃣ Arbitration Procedure in Dredging/Reclamation Delays

Notice of Dispute: Party claiming delay or additional costs notifies the other per contract.

Appointment of Arbitrator(s): Tribunal may include civil/marine engineering experts.

Project Schedule Review: Examine CPM/PERT charts, progress logs, weather and tidal records, and environmental permits.

Cause of Delay Analysis: Determine excusable vs. non-excusable delays, concurrent delays, and entitlement to extension of time.

Tribunal Findings: Determine liability, entitlement to damages, and adjustment of liquidated damages.

Remedies:

Extension of time (EOT)

Compensation for additional costs

Adjustment of liquidated damages

Termination remedies (if applicable)

Arbitration costs

7️⃣ Best Practices in Dredging and Reclamation Contracts

Detailed Scope and Technical Specifications: Include dredge depth, reclaimed land stability, sediment disposal methods.

Project Timeline and Milestones: Define critical path, float, and force majeure events.

Liquidated Damages & Penalties: Clearly specify methodology for delay calculation.

Arbitration Clause: Include seat, governing law, number of arbitrators, and technical expert appointment.

Documentation: Maintain daily progress logs, weather and tidal reports, correspondence, and change orders.

Variation/Change Order Protocol: Specify how additional work or environmental restrictions are handled.

8️⃣ Summary

Arbitration is the preferred forum for delay claims in dredging and reclamation of marina terminals due to technical complexity and commercial stakes.

Courts generally refer disputes to arbitration when a valid clause exists.

Tribunals rely on project schedules, expert reports, and contractual clauses to determine delays and liabilities.

Remedies include extensions of time, adjustment of liquidated damages, compensation for additional costs, and termination consequences.

Case law (Gammon, Aakar, DIAL v. L&T, Saw Pipes, Siemens, BALCO, Gannon Dunkerley) confirms enforceability of arbitration clauses, tribunal authority, and limited judicial interference.

LEAVE A COMMENT