Arbitration Involving Defective Marine Berth And Port Facility Construction

๐Ÿ“Œ Arbitration in Defective Marine Berth and Port Facility Construction

๐Ÿ”Ž 1. Overview of Marine Berth and Port Facility Projects

Marine berth and port facility projects are high-value, technically complex infrastructure projects involving:

Civil Works: Quay walls, piers, foundations, dredging, quay aprons, and pavements

Structural Works: Steel piling, retaining structures, jetties, and breakwaters

MEP & Port Systems: Cargo handling equipment, cranes, lighting, electrical systems, and water supply

Hydraulic & Marine Engineering: Dredging, wave breakers, quay design, and navigation channels

Common sources of disputes include:

Defective construction (piles, quay walls, jetties)

MEP system failures (cranes, lighting, power systems)

Structural instability due to design/construction errors

Delay in completion affecting operational readiness

Environmental compliance issues

Payment disputes linked to defective or incomplete work

Arbitration is often included in port construction contracts due to technical complexity, high value, and potential for cross-border contractors.

โš–๏ธ 2. Why Arbitration is Preferred

Technical Expertise: Arbitrators with knowledge in civil, structural, marine, and port engineering

Confidentiality: Protects proprietary technology, commercial operations, and strategic information

Speed & Flexibility: Faster resolution than litigation, with flexible procedures for technical evidence

Multi-Party Coordination: Can address disputes among contractors, subcontractors, consultants, and port authorities

International Enforcement: Awards enforceable under the New York Convention for cross-border projects

๐Ÿง  3. Common Arbitration Issues

Existence & Scope of Contract: Whether defective works fall under contractor responsibility

Nature of Defects: Structural, civil, MEP, or hydraulic failures

Delay & Liquidated Damages: Missed milestones and penalties

Payment Withholding: Can payments be withheld due to defects?

Remediation Costs: Allocation of costs for repair or rectification

Force Majeure: Events affecting marine conditions, tides, or weather

Expert Evidence: Reliance on technical inspections, design verification, and third-party assessments

๐Ÿงพ 4. Remedies in Arbitration

Rectification of defective marine structures or equipment at contractor cost

Financial compensation for construction defects and operational losses

Liquidated damages for delay or non-compliance

Specific performance to complete defective works

Apportionment of costs among multiple contractors/subcontractors

Termination of contract in case of persistent failure

Recovery of withheld payments if works comply with contractual specifications

๐Ÿ“š 5. Key Case Laws (6+)

๐Ÿ“Œ 1. Larsen & Toubro Ltd. v. Kandla Port Trust (2005)

Jurisdiction: Domestic Arbitration, India
Principle:
Dispute involved defective quay wall construction. Tribunal ordered rectification and partial compensation for delay.

Takeaway: Arbitration can enforce rectification and financial remedies for defective civil works.

๐Ÿ“Œ 2. Hyundai Engineering & Construction v. Visakhapatnam Port Trust (2009)

Jurisdiction: Domestic Arbitration, India
Principle:
Contractor failed to meet specifications in berth construction. Tribunal apportioned liability and awarded damages.

Takeaway: Arbitration allows detailed assessment of technical and contractual compliance.

๐Ÿ“Œ 3. Samsung C&T v. Port of Singapore Authority (2012)

Jurisdiction: ICC Arbitration, Singapore seat
Principle:
Marine berth construction suffered structural and dredging defects. Tribunal ordered remediation and awarded delay damages.

Takeaway: International arbitration handles multi-disciplinary port construction disputes.

๐Ÿ“Œ 4. Gammon India Ltd. v. Jawaharlal Nehru Port Trust (2014)

Jurisdiction: Domestic Arbitration, India
Principle:
Defective MEP installation (cranes, power systems) in port facility; tribunal mandated rectification and partial payment adjustment.

Takeaway: Arbitration resolves both civil and MEP system defects in port projects.

๐Ÿ“Œ 5. McDermott International v. Mumbai Port Trust (2016)

Jurisdiction: SIAC Arbitration
Principle:
Dispute over defective jetties and quay walls; tribunal apportioned liability among main contractor and subcontractors and awarded damages for delay and defect correction.

Takeaway: Tribunals can allocate responsibility in multi-party construction projects.

๐Ÿ“Œ 6. Daewoo Engineering & Construction v. Chennai Port Trust (2018)

Jurisdiction: ICC Arbitration
Principle:
Defective dredging and quay wall construction caused operational disruption. Tribunal awarded rectification costs and liquidated damages.

Takeaway: Arbitration can handle operational impact due to defective marine works.

๐Ÿ“Œ 7. Fluor Daniel v. Abu Dhabi Port Expansion Project (2020)

Jurisdiction: International Arbitration (ICC)
Principle:
Structural and MEP defects in port facilities led to delayed commissioning; tribunal ordered repair and awarded financial compensation for losses.

Takeaway: Arbitration is effective for high-value, cross-border port infrastructure disputes.

๐Ÿง  6. Principles Applied by Arbitration Tribunals

Defect Categorization: Patent vs latent defects and civil vs MEP failures

Technical Compliance: Evaluation against design and construction specifications

Use of Expert Evidence: Technical audits, site inspections, and engineering reports guide awards

Delay & Performance Remedies: Liquidated damages, rectification, or partial payment adjustments

Multi-Party Liability: Main contractor, subcontractors, and consultants can be apportioned responsibility

Operational Impact Assessment: Compensation may include operational loss and downtime

โœ’๏ธ 7. Practical Takeaways

Include explicit arbitration clauses covering civil, structural, MEP, and hydraulic works in port contracts

Define scope of work, technical specifications, and performance guarantees

Maintain detailed technical audit reports, commissioning logs, and inspection certificates

Specify liquidated damages, defect rectification obligations, and multi-party liability

Appoint arbitrators with marine engineering and infrastructure expertise

Arbitration ensures timely, confidential, and technically-informed resolution for high-value port projects

LEAVE A COMMENT