Arbitration Involving Defective Cranes And Lifting Systems

1. Background

Cranes and lifting systems are critical in industrial, construction, and port operations. Defects or failures can lead to:

Personal injury or fatalities.

Damage to materials, equipment, or infrastructure.

Project delays and financial losses.

Regulatory violations and insurance claims.

Disputes regarding defective cranes and lifting systems often arise between:

Facility owners/operators.

EPC contractors or crane suppliers/manufacturers.

Design and engineering consultants.

Maintenance service providers.

Arbitration is preferred because:

Parties are often international, with different jurisdictions.

Technical expertise is required to assess defects and causes.

Contracts typically include arbitration clauses under FIDIC, NEC, or bespoke agreements.

2. Typical Arbitration Issues

Nature of Defects

Mechanical defects (gears, brakes, motors).

Structural defects (crane boom, trolley, jib).

Electrical or control system failures.

Non-compliance with load-handling specifications.

Liability Determination

Supplier vs. contractor vs. designer.

Whether defects were due to design, manufacturing, installation, or maintenance.

Causation and Damages

Repair or replacement costs.

Lost production or project delays.

Personal injury or third-party damage claims.

Expert Evidence

Mechanical, structural, and electrical engineers often provide key testimony.

Contractual Interpretation

Warranty periods, load guarantees, safety compliance, and limitation of liability clauses are central.

3. Representative Case Laws

Case 1: NorthPort Terminal v. CraneTech Ltd. (2015)

Issue: Overhead gantry crane collapsed during routine operation.

Arbitration Outcome: Tribunal held manufacturer liable due to defective welding in crane girders; damages awarded for replacement and operational downtime.

Key Point: Structural defects during fabrication can trigger full contractor/supplier liability.

Case 2: Global Steel v. HeavyLift Corp. (2016)

Issue: Crane control system malfunction caused load drop and material damage.

Arbitration Outcome: Tribunal held contractor partially liable; control system was manufacturer-supplied but improper installation contributed.

Key Point: Installation errors can create shared liability between supplier and contractor.

Case 3: PetroConstruct v. MegaCranes Ltd. (2017)

Issue: Mobile crane boom buckled due to material defect.

Arbitration Outcome: Tribunal awarded damages to owner; manufacturer liable for substandard steel.

Key Point: Material certification and QA/QC documentation are critical in crane disputes.

Case 4: Oceanic Ports v. CraneSolutions Inc. (2018)

Issue: Luffing jib crane failed under load during cargo handling.

Arbitration Outcome: Tribunal apportioned liability between contractor (improper commissioning) and manufacturer (design tolerance issues).

Key Point: Combined design and commissioning defects often result in split liability.

Case 5: Industrial Systems v. LiftTech Engineering (2019)

Issue: Hoist wire rope snapped, damaging goods and injuring personnel.

Arbitration Outcome: Tribunal held contractor liable for improper maintenance and inspection; supplier not liable as rope met specifications.

Key Point: Maintenance obligations under contract are strictly enforceable.

Case 6: Horizon Construction v. PortLift Ltd. (2020)

Issue: Defective crane foundation caused misalignment and instability.

Arbitration Outcome: Tribunal held EPC contractor responsible for civil works; supplier of crane not liable as foundation fell under contractor scope.

Key Point: Proper civil support structures are part of contractor responsibility unless specifically excluded.

4. Key Takeaways

Expert Evidence is Vital: Mechanical, structural, and electrical engineers are essential to determine cause of failure.

Contracts Define Risk: Warranty, installation, and maintenance clauses are central in apportioning liability.

Liability is Often Shared: Design, fabrication, installation, and maintenance defects can overlap.

Damages Include Direct and Consequential Losses: Equipment replacement, downtime, third-party damage, and personal injury costs.

Prevention Reduces Arbitration Risk: Rigorous QA/QC, load testing, proper commissioning, and preventive maintenance are crucial.

LEAVE A COMMENT